SPRPT: A Screening Tool for Subsea Pipeline Route Planning
The first route for a new subsea pipeline is often drawn by hand: a line on a chart from the platform to the shore, bent around the obvious obstacles. Then the questions start. Is the seabed too steep? Where will the pipe span? Which existing pipelines does it cross, and how? How much trenching is needed in shallow water? Answering them one by one, in separate spreadsheets, takes weeks.
I built a local tool to do the first pass of that work in one run. It is called SPRPT, the Subsea Pipeline Route Planning Tool. You give it bathymetry, existing assets, the pipe data and the design criteria. It finds a route, fits a buildable alignment, designs the seabed preparation, checks the pipe against the main DNV codes, and writes a report with a Route Position List. This article explains what it does, what a report looks like, and where its limits are.
What goes in
The inputs are the ones a route engineer would collect anyway:
- Bathymetry as an XYZ file, with the coordinate system, the depth sign convention and the vertical reference declared by the user. None of these are ever guessed: a missing or invalid CRS stops the run.
- Existing pipelines, cables and other assets from a DXF or KML, with their diameter and whether they are exposed or buried.
- Exclusion zones and conditional zones, plus debris or boulder points to avoid.
- The new pipe: outside diameter, wall, coating and concrete thickness, densities, steel grade and lay tension.
- Metocean data: 1, 10 and 100-year waves and directional currents.
- Soil layers with strength and unit weight.
- Design criteria: minimum bend radius, maximum along-route slope, clearance to assets, mattress size and maximum layers, and the maximum trench cover.
Every grid and result carries a fingerprint, so a result can be traced back to the exact input and settings.
How a route is found
The tool turns the bathymetry and constraints into a cost surface. Each cell gets a cost from its slope, depth, roughness and distance to existing assets. Exclusion zones, land and missing data get infinite cost. A shortest-path search across this surface finds the cheapest corridor from start to end.
A raw grid path is not a pipeline route, so the next step fits a real alignment: straight sections joined by arcs no tighter than the pipe's minimum bend radius. The fitted route is then measured against the cheapest corridor. A ratio of 1.0 means nothing was lost; a higher ratio means the arcs had to leave the best corridor somewhere.
Two options, every time
Each study produces two options side by side:
- Option A crosses existing assets where that is cheaper, and designs the crossing with concrete mattresses.
- Option B reroutes around every asset with a fixed clearance and never crosses.
Comparing them answers the question a client usually asks first: is the crossing worth it, or is a longer route simpler?
Seabed preparation
For each option, the tool designs the seabed under the pipe:
- Cut and fill to bring the along-route slope within the limit, with side slopes of 1V:2H, and the volumes.
- Mandatory burial where the water is shallow. In the example below, the pipe is buried with 2 m of cover wherever the depth is under 13 m, following the applicable national pipeline regulation, and trenches are limited to a maximum cover of 3 m.
- A check of the effective cover: where the pipe bridges across the trench bottom instead of following it, the cover over the pipe is less than the trench depth suggests. The tool finds those stretches and deepens the trench, up to the maximum cover.
Engineering checks
Then the pipe is checked as it would lie on the designed seabed:
- Free spans to DNV-RP-F105: a screening check for in-line and cross-flow vortex-induced vibration, a simplified ultimate limit state, and VIV fatigue life where enabled. Spans that fail get grout-bag supports, with an estimated volume.
- On-bottom stability to DNV-RP-F109, using the absolute static method, giving the concrete thickness needed to keep the pipe stable in each condition.
- Pipe bending to DNV-ST-F101 combined loading, along the route and at every girth weld, plus the strain in the concrete coating at the field joints.
- Crossings: the vertical separation required by DNV-ST-F101, the number of mattress layers needed to reach it, and the crossing angle.
Each check is run for the as-laid, hydrotest and operation conditions, because they govern different things: the empty pipe spans differently from the full one, and operation adds pressure and temperature.
What a report looks like
The example is a short route of about 3 km from offshore into a shallow nearshore area, run with a 16-inch pipe and a maximum trench cover of 3 m. The comparison table at the top of the report gives the main numbers:
- Route length: 2,969 m for Option A and 3,133 m for Option B, against a straight line of about 2,893 m.
- Crossings: Option A crosses one existing pipeline at about 35°, needing 26 mattresses; Option B has none.
- Trenching: about 1.5 km of mandatory burial in each option, around 40,000 m³ of cut.
- Free spans after the seabed design: 19 failing in Option A, 9 in Option B, with 20 and 11 grout-bag supports.
- On-bottom stability: more than a kilometre of each route needs much heavier concrete than the assumed 24 mm.
- Pipe bending: Option A exceeds the limit over a short stretch near the shore end; Option B stays below it.
Both options are marked "fail" overall, and that is the useful part. The report does not pretend the route is ready. It shows which checks fail, where, and why: an oblique crossing where three mattress layers are not enough for the required separation, a crest that bends the pipe too much, and long stretches where the pipe is too light for the waves and current. Each of those is a clear task for the next design step.
The report also includes the full Route Position List (waypoints with KP, coordinates, depth, bearing and arc radius), a list of every girth weld with its utilisation, and the route is exported to DXF and KML for CAD and Google Earth.
Being honest about the inputs
Two sections of the report matter as much as the results.
The design criteria table lists every input with its source: "user" when it was entered for the project, a code clause when it comes from a standard, and "ASSUMPTION" when the tool used a placeholder, such as the trench width or the grout-bag footprint.
The standards register lists every code used, the clauses applied, and whether each clause was checked against a copy of the document ("verified") or not yet ("to verify"). Client criteria, such as the slope limit or the bend radius from the line pipe datasheet, are always "to verify" until someone cites the source document.
A screening tool that hides its assumptions is dangerous. One that lists them is a good starting point for a design review.
Limitations
- The result is a preliminary screening study, not a statement that a route is safe to install.
- The seabed is treated as rigid, so bending moments at crests tend to be higher than in reality.
- Stability uses the conservative absolute static method only.
- Volumes are indicative, from a smoothed seabed, not construction quantities.
- Spans outside the validity range of the simplified F105 method are flagged for finite element analysis.
- Features outside the study area do not affect the route, so relevant assets must be inside it.
What I took from building it
- Declare, never guess. Coordinate system, depth sign and vertical reference are the most common sources of silent errors, so the tool refuses to run without them.
- Show two options. Crossing versus rerouting is almost always the first decision, and seeing both with the same checks makes it an easy discussion.
- A failing result is still a result. The value is in showing where and why a route fails, early, before anyone has committed to it.
- Label every assumption. Engineers trust a screening tool more when it tells them exactly which numbers are placeholders.
- Keep it local and simple. It runs on a laptop, from a double-click, and one study at a time is enough for this stage of a project.